Help · Make: manufacturing

How to run a work order from start to finish

Issue material, record job cards and output, book scrap and see cost variance.

Who can do this: Admins and Accountants. Viewers can open it but not change anything.

Steps

Step by step

  1. Create a work order from a sales order, the planning screen or Make → Work orders → New.
  2. Transfer material to work-in-progress.
  3. Record job cards for each operation (time and operator).
  4. Finish: enter the quantity produced and any scrap.
  5. Bebaak consumes materials, adds finished goods to stock and shows actual vs standard cost.

Need a hand?

WhatsApp +91 97111 87655 or email siba@bebaak.co with your organisation name and a screenshot.

Contact support